Project Timeline

Construction is slated to start in mid-June 2013 and continue through 2015.

PHASE I: JUN 2013 to JAN 2014

•Utility relocations
•Seismic strengthening of tower (1-7)
•Preparations for sprinkler and fire alarm work
•Excavation of addition
•Scrape out of 2-story

PHASE II: NOV 2013 to JUN 2015

•Complete life safety/fire sprinkler work in 4-story
•Complete new 3-story building

PHASE III: JUN 2015 – DEC 2015

•Complete Paseo and 2-story renovation
•External concrete work and start landscaping
•GRAND OPENING!

timeline image of construction scheduleTimeline subject to delays. Click on the image above to view a larger version (pdf).